NEOEN SA (EPA:NEOEN) - CENACE suspends pre-operational testing at all Mexican solar and wind energy facilities, including Neoen’s El Llano solar farm

Transparency directive : regulatory news

07/05/2020 17:39

Click here to download pdf version

MEDIA RELEASE

Paris, May 7, 2020

CENACE suspends pre-operational testing at all Mexican solar and wind energy
facilities, including Neoen's El Llano solar farm

 * CENACE, the government body overseeing Mexico's electricity grid, has 
   decided to suspend pre-operational testing during the Covid-19 emergency at 
   all solar and wind energy facilities not yet in commercial operation

 * Neoen's El Llano photovoltaic power plant, which had begun injecting power 
   to the Mexican grid in February, is affected by these measures

On April 29, CENACE, the government body overseeing Mexico's electricity grid,
decided to suspend pre-operational testing at all solar and wind energy
facilities not yet in commercial operation from May 3 and during the Covid-19
emergency. This decision is one the measures announced by CENACE amid Covid-19
pandemic and the contraction in demand for electricity.

The decision applies to the El Llano solar plant owned and operated by Neoen,
as well as several dozen other power plants, accounting for several gigawatts
of green electricity capacity. As a result, El Llano had to halt its production
on May 3. Construction of the 375 MWp photovoltaic facility was completed at
the beginning of the year. It was in the process of pre-operational testing
with CENACE ahead of the scheduled entry into force of a long-term power
purchase agreement early July 2020. The El Llano power plant had started to
inject power to Mexico's electricity grid in February, with this energy being
sold in the spot market. Neoen's El Llano solar power plant generates some of
the world's most price-competitive electricity (less than $19 per MWh).

The EBITDA shortfall caused by the temporary shutdown of its El Llano facility
is estimated at up to $2 million per month. Neoen stands ready to put the El
Llano power plant back into service to recommence injecting power to the grid
and resume pre-operational testing as soon as CENACE lifts its suspension.
Neoen, which first moved into Mexico in 2013, remains firmly committed to
supplying the country with green, reliable, and cost-competitive energy.

About Neoen

Neoen is one of the world's leading and fastest growing independent producers
of exclusively renewable energy. With a capacity of more than 3 GW in operation
or under construction, Neoen is a high-growth company. Neoen is notably active
in France, Australia, Mexico, El Salvador, Argentina, Finland, Portugal,
Ireland, Zambia, Jamaica and Mozambique. In particular, Neoen operates France's
most powerful solar PV farm (300 MWp) in Cestas, and the world's largest
lithium-ion power reserve (150 MW/193.5 MWh storage capacity) in Hornsdale,
Australia. Neoen is targeting at least 5 GW capacity in operation or under
construction by end of 2021. Neoen (ISIN Code: FR0011675362, ticker: NEOEN) is
listed in Compartment A of the regulated market of Euronext Paris.

For more information: www.neoen.com

Contact

Neoen

communication@neoen.com

Media

OPRG Financial

Isabelle Laurent
+33 1 53 32 61 51
Isabelle.laurent@oprgfinancial.fr

Fabrice Baron
+33 1 53 32 61 27
Fabrice.baron@oprgfinancial.fr


Other stories

19/05/2024 17:21
19/05/2024 15:24
19/05/2024 10:15
19/05/2024 00:55
19/05/2024 10:14
19/05/2024 09:00
19/05/2024 12:10
19/05/2024 17:15
19/05/2024 15:18
19/05/2024 14:16
19/05/2024 13:09
19/05/2024 05:47
19/05/2024 13:38
19/05/2024 16:08
19/05/2024 09:33
19/05/2024 16:16
18/05/2024 22:12
19/05/2024 17:04
19/05/2024 13:30
19/05/2024 13:21
18/05/2024 14:29
18/05/2024 14:40
19/05/2024 15:29
18/05/2024 22:56
19/05/2024 14:41
19/05/2024 03:44
19/05/2024 17:31
19/05/2024 16:28
19/05/2024 16:18
19/05/2024 11:37
19/05/2024 15:13
19/05/2024 10:00
19/05/2024 08:30
19/05/2024 01:29
19/05/2024 15:14
19/05/2024 14:29
19/05/2024 11:50
18/05/2024 19:16